Category: Hartwell
Rippling Cove-Keowee-6
February 20, 2018
No Comments
Foundations have been poured and now the basement is being framed out and septic lines run. It's really starting to come together.
Read More →
Tammerick-Hartwell-5
February 13, 2018
No Comments
You can see all the walls, doorways and window placement for the basement.
Read More →
Little Lightwood-Hartwell-5
February 6, 2018
No Comments
You can start to see the layout of the different rooms and the locations of the doors and windows.
Read More →
Timberbrook-Keowee-5
January 30, 2018
No Comments
This site had tons of large rocks that are now being put to use in creating walls to assist with soil retention while looking very ...
Read More →
Rippling Cove-Keowee-5
January 23, 2018
No Comments
We've dug up more rock than expected so the grading and digging of the basement has taken longer than initially scheduled.
Read More →
Tammerick-Hartwell-4
January 16, 2018
No Comments
The wall forms were put into place and the concrete poured into them creating foundation walls for the basement.
Read More →
Little Lightwood-Hartwell-4
January 9, 2018
No Comments
You can see the poured walls and foundation allset. The rough in plumbing is set in place and all backfilling is just about complete.
Read More →
Timberbrook-Keowee-4
January 2, 2018
No Comments
This home's story has hit a slight bump, we found boulders.
Read More →
Rippling Cove-Keowee-4
December 26, 2017
No Comments
We've dug up more rock than expected so the grading and digging of the basement has taken longer than initially scheduled.
Read More →
Tammerick-Hartwell-3
December 19, 2017
No Comments
The site is being cleared and graded in preparation for building the new home. Here we're showing the views that will be had from the ...
Read More →